Deck Construction Cost Estimator
Quantities from IRC R507.6, R507.5(1) and AWC DCA 6 Table 4
Most deck cost pages quote a national average with no source and no date. This one counts the actual materials your deck needs, then lets you price them at your own yard.
Deck cost estimate
Quantities are sized against IRC Table R507.6, IRC Table R507.5(1) and AWC DCA 6 Table 4. Prices are pre-filled from a range another publisher printed, attributed and dated below. Change them to yours.
Specification summary
Generated from on . Reopen that address to reproduce these figures exactly.
Entered
Result
Worked example
- The frame is sized first. IRC Table R507.6 gives the joist that spans 12 ft at 16 in centres, and R507.5(1) gives the beam. That decides how much timber there is before any price is applied.
- Footings follow the beam. The post spacing sets the Table 4 row, which gives the footing diameter, and the diameter and your depth give the concrete volume in bags.
- Then the quantities are counted. Joist linear feet, beam plies, decking rows and linear feet, screws at two per crossing, one hanger per joist.
- You supply the prices. Enter what your yard actually charges per foot and per bag. Leave a line blank and it stays a quantity rather than becoming a guess.
- The total is arithmetic. Quantity times your price, plus optional labour per square foot, divided by the area for a cost per square foot you can compare against a quote.
The formula
- quantity
- counted from the code-sized frame, not estimated per square foot
- your price
- what your yard quotes, today, for that item
- area
- deck width times length, in square feet
- No national average, no regional multiplier, no index. Those are the parts other cost pages invent.
Why there are no prices on this page
Published price ranges, and whether they have aged
What the estimate leaves out
Comparing this against a contractor's quote
Frequently asked questions
- Why does this not just tell me what a deck costs?
- Because nobody can, honestly. Lumber pricing is regional and moves weekly, so a published figure is stale almost immediately. What is stable is the quantity of material your deck needs, and that is what this page computes.
- How much does a 12x16 deck cost?
- That depends entirely on your lumber prices, and anyone quoting a single national figure is guessing. This page tells you exactly what a 12 ft by 16 ft deck needs in joists, beam, posts, footings, decking and fasteners. Price those at your yard for a real answer.
- Does it include labour?
- Only if you enter a labour rate per square foot. There is no default, because labour rates vary more than materials do.
- Are the quantities the same as the deck materials calculator?
- Yes. Both read the same code tables through the same build-time data, and a build-time check compares them across 75 deck configurations.
- Should I add waste?
- Yes. The takeoff is exact, with no allowance. Most builders add 5 to 10 per cent on decking, and more where there are mitres or a picture-frame border.
- Why is the frame sized before the price?
- Because the frame decides the quantity. You cannot count joists until you know whether the span needs a 2x8 or a 2x10, and that comes out of IRC Table R507.6, not out of a price list.
Check these numbers yourself
- IRC R507.5 and R507.6: deck beams and joistsUpCodes. The span tables that size the frame the quantities are counted from.
- AWC DCA 6: Prescriptive Residential Wood Deck Construction GuideAmerican Wood Council, free PDF. Table 4 for the footing schedule.
Figures on this page last checked against the source documents on 2026-09-06. Codes are amended locally; confirm against the edition your jurisdiction enforces.
Related calculators
Estimates only. Quantities are a takeoff from prescriptive code tables for a rectangular ledger-attached deck, with no waste allowance and no ledger, stairs, guard, hardware, permit or site-work costs included. Prices are whatever you enter; this site publishes none. Confirm quantities against your own drawings and prices against your supplier before you buy.